New library construction meeting milestones

image_pdfimage_print

The Lions Park Projects construction continues and scheduled milestones are being met.

The steel reinforced concrete foundations, and infrastructure for water, sewer, gas and power utilities for the new library have been surveyed and constructed.

The structural steel frame system for the building has been erected, welded, bolted, inspected, and secured in place. The framework for the large, oval shaped sky light above the future staircase is taking form. The aesthetic arches of the building’s exterior are now visible.

On March 7, the concrete for the library’s first floor was constructed, including all utility penetrations, elevator pit and connections to its adjacent vertical components. On March 19, the concrete for the second floor of the building was placed. Underground storm drain construction is also underway for the new, one-acre park.